A long Jira state locates a possible wait. It does not establish the cause.

The delivery review has reached the missed release commitment. Someone opens Jira and sorts completed items by time in status. Review has the longest stays. The proposed fix is to give reviewers a tighter turnaround target.

Before agreeing, open one of those items. Was it ready for review when it entered the state? Did it need a product decision? Had the review finished elsewhere while the ticket remained untouched? The chart has identified somewhere to look. The proposed target already assumes an explanation.

Recorded state duration can locate a possible wait, but it does not establish the cause or show whether the wait harmed delivery.

That boundary matters when a delivery manager must decide whether to reserve reviewer capacity, change a handoff, or leave a necessary control alone. Each decision needs more than a long bar on a dashboard.

A state name does not describe everything that happened

A status history records transitions and their timestamps. Subtract one timestamp from the next and you get elapsed time under a label. Unless the workflow records them separately, that interval does not distinguish active work from waiting.

Consider an item labelled "In review". Its recorded stay might include a reviewer reading the change, the author correcting it, and a pause while someone clarifies acceptance criteria. It might also include time after approval because nobody moved the ticket. These are possible explanations, not findings about your team. They would require different responses.

Even a confirmed wait needs interpretation. Holding a change until a necessary safety check finishes is different from leaving it unassigned because nobody knows who should check it. A shorter state duration is not sufficient evidence of better delivery. You need to know what the wait protected, what it delayed, and whether removing it would move the cost elsewhere.

This is where Jira workflow bottleneck analysis becomes an investigation rather than a ranking exercise.

The evidence supports finding the question

Coremans et al. (2023) used Jira histories to examine software processes in one department of a large international company. The histories exposed differences between teams and issue types, repeated loops, and long stays in particular states. They also revealed interactions that version-control data did not show.

That is useful evidence for a delivery review. A source-code history cannot describe every clarification or handoff surrounding a change. Issue histories provide another view of the work and help identify patterns worth examining. In this study, long recorded waits were prompts for further investigation, rather than proof of what caused them.

The distinction survives a change of setting. Urrea-Contreras et al. (2024) examined two software-development projects in one small or medium-sized enterprise. Their process analysis exposed different paths through the workflow and uneven durations across states, including long stays that averages alone would obscure. Extraction, documentation and cross-system linkage constrained the interpretation.

Read together, these cases support using event histories to narrow a broad complaint such as "delivery takes too long" into a question about particular items and transitions. They do not justify treating the state with the most accumulated time as the cause of missed commitments. The workflow label describes where the system recorded an item. Its meaning still depends on local practice and on what the records leave out.

Vavpotič et al. (2022) examined that interpretive problem by combining Jira-derived logs with stakeholder perceptions in an Austrian software SME. The combined analysis produced recommendations unavailable from either source alone. The case involved five developers, so it carries limited weight as a general prescription. The authors also retained a role for expert interpretation rather than offering a universal analysis recipe.

Combining these sources should involve checking one against the other. If someone recalls that an item was waiting for approval, look for the request and the response. If the log shows a long stay that nobody remembers, inspect the surrounding work before accepting a convenient explanation. People supply context, but their recollections are not automatically more accurate than timestamps.

The evidence remains case-based. None of these studies establishes that the diagnostic below improves predictability or quality across organizations. Azure DevOps was not directly studied. Applying the same reasoning there rests on comparable event-history mechanics, with the same need to check what states and timestamps actually represent.

Start with a small set you can explain

Take the last 20 finished items from one coherent workflow and item class. Keep production defects separate from feature work if their routes and controls differ. Use a consistent definition of finished, and note any workflow changes within the sample.

Compare elapsed time by recorded state. Keep each visit visible when an item returns to a state, as well as its total time there. Look at the spread and the longest stays alongside the average. A state that holds nearly every item deserves a different question from one with a single exceptional stay.

This finished-item sample has a blind spot: it excludes work still stuck. Use it to investigate completed histories, not to declare the current system healthy. Check open aged items separately before drawing conclusions about present delivery risk.

Select the five longest recorded state intervals. Read the item histories with people who supplied and received the work. Ask what had to happen before each item could move, when that became possible, and what evidence supports the account. Jira comments, blocker fields, linked review records, decisions and test results may resolve a question that state-transition timestamps alone cannot.

Classify the causes before choosing a change. Useful categories include decision, dependency, capacity, clarification, policy or control, technical feedback, legitimate queue, and data artefact. Allow mixed causes and unresolved cases. Forcing an uncertain account into "capacity" merely gives the original assumption a field in a spreadsheet.

Keep names out of performance comparisons. An assignee may have spent most of the interval waiting for something outside their control. This exercise concerns operating conditions around the work, not a ranking of individual speed.

Change one condition and keep the quality check

If several inspected items support the same explanation, choose one operating condition to test. Suppose the histories confirm that ready items repeatedly waited for a review slot. Reserving a review slot would be a reasonable experiment. If the items instead lacked acceptance criteria, extra reviewer capacity would leave that problem intact.

Record the proposed explanation and expected change before starting. Retain the existing review or safety control and a quality guardrail, such as monitoring escaped defects. Observe comparable work for four weeks, checking whether the identified wait changes without more rework or poorer quality.

Treat this as a practical experiment, not a validated intervention. A small sample and a short observation period will leave uncertainty. At the next review, bring the inspected items, the supported cause classification, and the result of that one change. If the explanation remains unresolved, assign the next evidence check before assigning anyone a faster turnaround target.

References

Coremans, B., Klomp, A. L., Rukmono, S. A., Krüger, J., Fahland, D., & Chaudron, M. R. V. (2023). Process Mining from Jira Issues at a Large Company. In 2023 IEEE International Conference on Software Maintenance and Evolution (ICSME) (pp. 425–435). IEEE. https://doi.org/10.1109/icsme58846.2023.00055

Urrea-Contreras, S. J., Astorga-Vargas, M. A., Flores-Rios, B. L., Ibarra-Esquer, J. E., Gonzalez-Navarro, F. F., Garcia Pacheco, I., & Pacheco Agüero, C. L. (2024). Applying Process Mining: The Reality of a Software Development SME. Applied Sciences, 14(4), 1402. https://doi.org/10.3390/app14041402

Vavpotič, D., Bala, S., Mendling, J., & Hovelja, T. (2022). Software Process Evaluation from User Perceptions and Log Data. Journal of Software: Evolution and Process, 34(4), Article e2438. https://doi.org/10.1002/smr.2438

AI disclosure: AI was used to help create this article. Responsibility for the published content remains with Nico Thümler.